NLC Beam Delivery Collimation System
1. Mission/Requirements
1.1 Problem Statement
1.2 Customers
1.3 System Boundaries
System Definitions -
Lehman version, Spring '99
1.4 Performance Requirements
Collimators - Lehman version,
Spring '99, including all NLC areas
2. Functional Analysis
2.1 Generic system descriptions
2.1.1 Overall system
2.1.1.1 Sub-systems
2.2 Operating modes
3. System Synthesis/Analysis
3.1 Tradeoff Studies
3.2 Alternatives Analysis
Consumable Collimator R&D
3.2.1 Technical analysis
3.2.2 Cost Analysis
3.3 Baseline System Synthesis
3.3.1 Baseline Technical Description
3.3.2 Baseline Cost
Collimators - Lehman version,
Spring '99, including all NLC areas
3.3.3 Baseline Schedule
3.3.4 Baseline Risk
4. System Integration/Verification
4.1 Interface Agreements
4.2 Verification Plans
Additional Information
This page was created 03/16/2000 by Eric Doyle